GRAFFITI REMOVAL & OIL SPILL CLEAN UP

Caerphilly County Borough Council - Pont Joe Calzaghe Bridge, Caerphilly

Client's Challenge

Caerphilly County Borough Council required an immediate emergency response following a significant diesel spill along a section of the A465 dual carriageway at Pont Joe Calzaghe Bridge.

An oil tanker incident had released a large volume of diesel across the highway surface, creating an immediate and serious safety hazard for road users. The contamination significantly reduced surface grip and posed a high risk of secondary incidents if not addressed urgently.

Due to the scale of the spill, its location on a major traffic route, and the risks involved, the council required a specialist emergency oil spill clean-up contractor capable of:

• Rapid out-of-hours mobilisation
• Operating safely within a live highway environment
• Working under strict traffic management controls
• Effectively removing diesel contamination from the carriageway
• Restoring safe driving conditions as quickly as possible

Assessment & Planning  

APT ICC attended site as part of an emergency response and immediately
assessed:

• The extent and spread of diesel contamination across the carriageway
• The condition and type of road surface affected
• The most effective degreasing and wash-down methodology
• Jetting pressures required to remove contamination without surface damage
• Traffic management and safety requirements for operatives and road users
• Recovery methods needed to remove residual fluids and contaminants

A rapid-response plan was implemented focusing on containment, aggressive degreasing, controlled high-pressure jetting and full surface recovery, ensuring the road could be returned to a safe condition without delay.

Methodology

APT ICC attended site as part of an emergency response and immediately
assessed:

• The extent and spread of diesel contamination across the carriageway
• The condition and type of road surface affected
• The most effective degreasing and wash-down methodology
• Jetting pressures required to remove contamination without surface damage
• Traffic management and safety requirements for operatives and road users
• Recovery methods needed to remove residual fluids and contaminants

A rapid-response plan was implemented focusing on containment, aggressive degreasing, controlled high-pressure jetting and full surface recovery, ensuring the road could be returned to a safe condition without delay.

Graffiti Removal from Sirhowy Bridge in Blackwood, Gwent

Site Access & Logistics

Graffiti Removal from Sirhowy Bridge in Blackwood, Gwent

Equipment
• Industrial high-pressure water jetting equipment
• Industrial road sweeping and suction recovery units
• Traffic management and coning systems
• Full PPE for live highway emergency response

Chemicals
• UltraMax 2020 – high-performance industrial degreaser used to penetrate hard surfaces and lift diesel and oil contamination effectively

The Results
• Diesel contamination successfully removed from the carriageway
• Road surface restored to safe driving conditions
• Traffic disruption minimised through controlled lane management
• Residual contamination fully recovered using industrial equipment
• Emergency works completed safely and compliantly

APT ICC’s rapid mobilisation, specialist equipment and controlled methodology enabled Caerphilly County Borough Council to reopen the affected section of the A465 safely and without further incident, preventing escalation and protecting public safety.